PFI was designed as a means to transfer risk to the party best able to manage it. A well designed PFI project contract will represent a better way to share all types of risk - responsibilities are negotiated at contracting stage, assessed on a case by case basis and assigned appropriately to the parties involved, according to who is best able to manage the particular risk.
Initial design
Ability of that design to deliver the facilities requested by the client
SPC, passed to Building Contractors
Initial design
Incorrect specification of design by the client resulting in an inappropriate building or part thereof
The client (e.g. NHS Trust, Local Council)
Construction
Cost of delays, inability to deliver the design, quality of work
SPC, passed to Building Contractors
Service Provision (e.g. Catering, laundry, waste disposal, grounds maintenance, etc.)
Cost of non-performance, unexpected price increases
SPC, passed to FM service provider
Lifecycle (maintenance and upkeep of buildings, fixtures and fittings)
Unexpected costs, price increases
SPC, and/or passed toFM provider
Utilities
Price increases, unavailability
The client
Vandalism to property
Costs incurred for repair
Shared
Failure of a public service
Failure of front line services, e.g. shortage of nurses, teachers strike
The client
Risk is often shared in a contracted arrangement. For instance, the SPC may pay a fixed portion of increases in insurance, and the client pays any costs beyond this threshold.
It is typical that, for each aspect of the project, a risk register is produced and updated regularly to keep management focus on project issues. For instance, Laing SPCs produce a risk register to manage the risks to which it is exposed. The register catalogues the various risks, and assigns each one a number on the scale 1-3 of both the likelihood of their occurrence and the financial impact should they happen. The two numbers are multiplied to give the final rating, allowing the greatest risks to be highlighted and acted upon. Mitigation procedures are also recorded in the register, devised to reduce the overall risk rating and therefore make them less of a concern in the project.